Building regulations for septic tanks and treatment plants
Installing a new septic tank or treatment plant needs building regulations approval. Approved Document H, part H2, sets out how it should be done.
You need approval
GOV.UK says you need building regulations approval to install a new septic tank or small sewage treatment plant, and you may need planning permission too. If your current system was never approved, you may need to apply when you change it.
Key distances from Approved Document H
| What | Distance |
|---|---|
| Septic tank from habitable parts of buildings | At least 7m |
| Septic tank from tanker access | Within 30m |
| Treatment plant discharge from watercourses and other buildings | At least 10m |
| Drainage field from any watercourse or permeable drain | At least 10m |
| Drainage field from any building | At least 15m |
| Drainage field from a groundwater supply abstraction | At least 50m |
Other requirements
- Plants should be type-tested, and if they need power, cope without it for up to 6 hours or have a backup supply.
- A notice should be fixed inside the building describing the maintenance needed.
- No driveways, paving or other services in the drainage field area.
We handle it
We prepare the drawings and information building control needs and arrange inspections as part of every replacement.
Checked against GOV.UK guidance: 24 November 2026. Rules apply to England.
Get a fixed, written quote
Free site visit across Yeovil and an hour around. We tell you straight what you need, what it costs and how long it takes.